Arrow Electronics 10/01/2009
Managing Customer Expectations During Turbulent Market Conditions
We must secure the best possible view of forward-looking customer requirements, preferably through hard purchase orders placed at
or beyond current lead times.
Over the past 13 weeks we have observed and measured increasing lead times and other signals of supply constraints across multiple
suppliers and commodities. Throughout the downturn, we have also witnessed
shorter and shorter forecast visibility from our customers. In addition, many
suppliers have decreased their production capacity significantly. These factors
create the potential for significant supply-chain disruptions for your
customers.
As lead times continue to be pressured and in many cases, increase, it is critical that we continue to reach out to all of our
customers to ensure their awareness of the market dynamics that make it
difficult to fulfill unforecasted or upside demand. The best way for Arrow to
support the customers seeing healthy business demands for their products remains
increased visibility to forward-looking demand and whenever possible, the
placement of hard POs for future delivery.
It is important to note that even if global market demand eases toward the end of the year, it will still take weeks for fab and
test and assembly investments to have a positive impact on lead times. If global
market demand stays flat or increases, lead times will remain challenged as
additional working capital investments are analyzed.
For competitive reasons, we will not publish the supplier names. The following information was collected during the week of
September 21st.
Tier 1 Programmable Logic Supplier –
Increasing lead times up to 16 weeks through Q4.
Tier 1 Analog Supplier – Capacity constraints have pushed lead times up to
20 weeks.
Tier 1 Embedded Supplier – Increasing MCU lead times from 4-6 to 18-20 weeks
due to test capacity.
Tier 1 Discrete Supplier – Lead times stretching up to 10-12 weeks in the
SOT-23 package.
Tier 1 Broad Line Semiconductor – Lead times increased up to 16-20 weeks and existing backlog rescheduled up to one month from original commitment due to test and
assembly constraints.
Tier 1 OPTO Supplier – Allocation on opto-couplers.
Tier 1 Memory Supplier – Lead times up to 14 weeks.
Tier 1 Broad Line Supplier – Potential allocation across multiple technologies by end of Q3.
Passive Segment – Lead times increasing on SMT tantalum capacitors A and B
case sizes 18-26 weeks. Factory allocation on SMT ceramic Hi-Cap (all case sizes
1 uf and greater cap value).
Power Supplies – Current lead times are averaging 16 weeks depending on
the supplier. Some lead times are stretching due to material shortages.
Switch/Relay Segment – Current lead times are averaging 12-16 weeks depending
on the supplier.
Connector Segment – Lead times extending as suppliers get production lines
back up and running due to latest increase in demand.
Because we expect the extended lead times to continue at least through the end of the
year, we will continue to monitor demands and increase our on-order and stock
positions in the most challenged technologies. However, please note that an
increasing percentage of customer demand is on single- and limited-customer
devices, which are much more difficult to manage through speculative purchases
in a capacity-constrained market. Again, we must secure the best possible view
of forward-looking customer requirements, preferably through hard purchase
orders placed at or beyond current lead times.